Quiz-summary
0 of 6 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
Information
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
Results
Results
0 of 6 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- Answered
- Review
-
Question 1 of 6
1. Question
A project wants to order a complex set of laboratory equipment and asks you as the local procurement officer to grant the companies a period of only two days to submit their bids. What should you do?
CorrectIncorrect -
Question 2 of 6
2. Question
A project asks you to order various tool materials directly from company B (value EUR 3,500). The project has already obtained and assessed three bids on its own initiative.
Which of the following statements is correct in this situation?
CorrectIncorrect -
Question 3 of 6
3. Question
In a formal invitation to tender, an employee of one of the competing suppliers calls you and asks for further explanations of the procedure and of some details of the technical specifications. What should you do?
CorrectIncorrect -
Question 4 of 6
4. Question
A bid in a formal invitation to tender is received in the proper form and in time but varies from the specifications set out in the tender documentation on the basis of a telephone arrangement with the officer responsible for the commission at the project in question. As the number or level of specifications has been considerably reduced under this arrangement, the bid offers a much cheaper product than any of the other competitors.
CorrectIncorrect -
Question 5 of 6
5. Question
Shortly before the deadline for bids, notification is received from several participants that some details of the specifications are incomprehensible. It is not possible to clarify this with the officer responsible for the commission in time. What do you need to do?
CorrectIncorrect -
Question 6 of 6
6. Question
What is meant by the term “bid validity/binding period”?